Councils from all five affected Durham municipalities unanimously approve motions urging EA on Line 9

As of March 24th, all five lakefront communities in Durham (the ones that Line 9 passes through) have approved motions calling on the province to require a proper environmental assessment on Line 9, and in addition, asking that the pipeline be upgraded over a reasonable time period to 3/8" thickness rather than the current 1/4" That constitutes 97% of the existing pipe.

These motions were urged on the Councils by DurhamCLEAR president, Doug Anderson, who made delegations to all of them.

A copy of the motion from Pickering (they were all quite similar - Pickering was the last) can be seen here.